Weekly Construction Updates

Construction Notice 2.5.2021
February 5, 2021

Construction Notice 2.5.2021

The Climate Pledge Arena team celebrated a huge milestone last week with the topping out ceremony!  A Seattle Center Campus power outage has been scheduled for Wednesday, Feb. 10 at…

Read More
Construction Notice 1.29.2021
January 29, 2021

Construction Notice 1.29.2021

The Arena tunnel is OPEN!  The tunnel entrance is on 1st Ave N between John St. and Thomas St.  Interior work continues with suites, bathrooms and other spaces undergoing mock-ups…

Read More
Construction Notice 1.22.2021
January 22, 2021

Construction Notice 1.22.2021

The Arena tunnel is projected to be operational starting January 25th.  The tunnel entrance is on 1st Ave N between John St. and Thomas St.  Use of the tunnel will allow for the closure of the temporary ramp located at the NE corner of 1st Ave N and Thomas St. 

Read More
Construction Notice 1.15.2021
January 15, 2021

Construction Notice 1.15.2021

On December 14th a new MPPCNV was approved by SDCI.  This has replaced the existing MPPCNV and was activated on January 13, 2021.  On Wednesday, January 6th, the Seattle Landmark…

Read More
Construction Notice 1.8.2021
January 8, 2021

Construction Notice 1.8.2021

On December 14th a new MPPCNV was approved by SDCI.  This will replace the existing MPPCNV.  The required public notice was issued on Tuesday, December 29th.  The new MPPCNV will…

Read More
Construction Notice 12.31.2020
December 31, 2020

Construction Notice 12.31.2020

On December 14th a new MPPCNV was approved by SDCI.  This will replace the existing MPPCNV.  The required public notice was issued on Tuesday, December 29th.  The new MPPCNV will…

Read More
Construction Notice 12.24.2020
December 23, 2020

Construction Notice 12.24.2020

Work to finish the tunnel includes shotcrete and waterproofing. The tunnel is projected to be operational next month. Noise generating activities are underground, which help reduce levels.  Noise mitigation enhancement is…

Read More
Construction Notice 12.18.2020
December 18, 2020

Construction Notice 12.18.2020

Work to finish the tunnel includes shotcrete and waterproofing.  Noise generating activities are underground, which help reduce levels.  Noise mitigation enhancement is continually being evaluated and installed. Interior work continues…

Read More
Construction Notice 12.11.2020
December 11, 2020

Construction Notice 12.11.2020

The atrium steel structure is complete.    Work to finish the tunnel includes shotcrete and waterproofing.  Noise generating activities are underground, which should help reduce levels.  Noise mitigation enhancement is…

Read More
Construction Notice 12.4.2020
December 4, 2020

Construction Notice 12.4.2020

The atrium steel structure is complete.    Work to finish the tunnel includes shotcrete and waterproofing.  Noise generating activities are underground, which should help reduce levels.  Noise mitigation enhancement is…

Read More
Construction Notice 11.27.2020
November 27, 2020

Construction Notice 11.27.2020

Temporary Roof Support has been dismantled.The atrium entry continues to take shape on the South side.    Work to finish the tunnel includes shotcrete and waterproofing.  Noise generating activities are…

Read More
Construction Notice 11.20.2020
November 20, 2020

Construction Notice 11.20.2020

The atrium entry continues to take shape on the South side.   Tunnel excavation on the South Parcel is complete!  Work to finish the tunnel includes shotcrete and waterproofing.  Noise generating…

Read More