CLIMATE PLEDGE ARENA at SEATTLE CENTER
CONSTRUCTION NOTICE
June 11, 2021

Along with the Arena opening, the Seattle Department of Transportation has designed improvements that include curbside modifications, enhanced Uptown and Arena access through transit, bicycle and pedestrian improvements. To learn more about how SDOT and Climate Pledge Arena are improving multi-modal transportation options in the Uptown neighborhood in 2021, visit www.seattle.gov/transportation/nodomap or www.climatepledgearena.com/transportation
As identified in the map above, street and sidewalk improvements are in progress. This work will include use of heavy equipment that will be impactful and generate noise. It is in progress at the following locations:
- Starting Tuesday, June 15th, Thomas St between Queen Anne Ave and 1st Ave N will be closed to vehicular traffic. This closure will be in place through the end of June. Pedestrian access will be maintained.
- Starting Tuesday, June 15th, the alley between Queen Anne Ave and 1st Ave N and Harrison St and Thomas will have no vehicular access from Thomas St during business hours (7 am-4pm). All alley traffic from residential parking will be directed northbound to Harrison St. This closure will be in place through the end of June.
- NE corner of Queen Anne Ave and Thomas St is ongoing and will continue through mid-June.
- Paving of the intersection of 1st Ave N and Republican St will be performed June 16th & 17th.
- Paving of the intersection of 1st Ave N and Harrison St will be performed June 16th & 17th.
- Installation of the protected bike lane on the west side of 1st Ave N between Denny Way and Thomas St has been pushed back and the start date is TBD.
Proper signage, staffing and safety measures will be in place at all locations.
SDOT approved the use of 2nd Ave for inbound and outbound trucks during the hours of
7 am–10 pm Mon.–Fri. and 9 am–10 pm Sat., Sun., and Holidays.
SDOT approved routes for all hours include westbound on Thomas St. to southbound Queen Anne Ave. N.
The Arena MPPCNV is activated.
Construction is allowed 24/7. Impact work hours are limited to daytime work only.
Construction Impact Work Hours:
Monday- Friday 8 am – 5 pm impact work
Saturday/Sunday/Holidays
9 am – 5 pm impact work
Interior Work – All work will progress during daytime hours, which includes Saturdays and Sundays from 9 am – 5 pm for impact work. All other work will occur as permitted by the MPPCNV.
- Prep work for installation of the dual scoreboards is advancing.
- Utility testing continues.
- Roof work including drainage repair, cleaning and painting is underway.
- Office spaces are being built out and finished.
- Installation of acoustical panels continues.
- Work to connect to the City water system is underway.
- Installation of solar panels on the Alaska Airlines Atrium roof continues.
- Sections of the sound wall continue to be removed as work on the exterior progresses.
- Installation of seats, safety glass and railing continues.
- Interior spaces are taking shape as work progresses with elements including fireproofing, sprinkler systems, lighting, framing, drywall work, painting, carpet installation and finishing work.
- Build out of the retail space and concession stands continues.
- Power and lighting are being switched over from temporary to permanent, where possible.
- Catwalk work and installation of lighting on the rigging grid continues during nighttime hours.
- Tile and millwork continue on multiple levels.
- Build out of ingress/egress at all four corners on the exterior plaza continues.
- Exterior stairs and elevation work is underway.
- Installation of utilities on the South Parcel is underway.
North Courtyard – Renovation of the North Courtyards (upper and lower) continues. The Courtyards are closed to the public and access will be limited to Seattle Center staff and Resident Organizations. Proper staffing and safety measures are in place. Courtyard work will be done during daytime hours only. As part of the North Courtyard renovation, SDCI has granted approval for the removal of the north segment of the sound wall with the condition that the Arena’s historic curtain wall is sealed.
Upgrades to the upper NW breezeway between KEXP and The Vera Project are underway. Improvements include the removal of the storage rooms, replacement of the concrete and waterproofing, and structural reinforcement of the slab.
Work hours are weekdays 7:00 am – 3:00 pm. This work is projected to continue through September 1st and the breezeway will be closed to pedestrian access for the duration of the project.
Bi-Weekly Arena Meeting – Open to all, the bi-weekly Arena meetings are open house forums to provide project updates and coordinate with stakeholders including but not limited to local businesses, communities, SDOT, SDCI and Seattle Center resident organizations on construction impacts and efforts to support ongoing activities at Seattle Center and in the adjacent communities.
Upcoming schedule:
Date Time Location
June 24th 6 pm Zoom Virtual meeting – https://seattlekrakenhockey.zoom.us/j/97458901069
CONSTRUCTION HOTLINE: (206) 401-9896