CLIMATE PLEDGE ARENA at SEATTLE CENTER
CONSTRUCTION NOTICE
APRIL 9, 2021
The swing crane has been dismantled and removed from the project.
Connection of Arena sewer lines to City systems is suspended. This work will resume the weekend of April 17 and continue through the first week of May. When this work resumes, it will include a left lane closure and weekday work from April 17 through April 23.
This work is weather dependent.
Along with the Arena opening, the Seattle Department of Transportation has designed improvements that include curbside modifications, enhanced Uptown and Arena access through transit, bicycle and pedestrian improvements. To learn more about how SDOT and Climate Pledge Arena are improving multi-modal transportation options in the Uptown neighborhood in 2021, visit www.seattle.gov/transportation/nodomap or www.climatepledgearena.com/arena/transportation.

As identified in the map above, street and sidewalk improvements are in progress. This work will include use of heavy equipment that will be impactful and generate noise. It is in progress at the following locations:
- Queen Anne Ave. between Mercer St. and Republican St. is ongoing and projected to continue through April 14.
- Queen Anne Ave between Republican St. and Harrison St. is ongoing and projected to continue at that location through April 14.
- Queen Anne Ave between Harrison St. and Thomas St. is ongoing and will continue through April 23.
- NW corner of Queen Anne Ave and Thomas St. is ongoing and will continue through April 30.
- NW corner of 1st Ave N and Republican St. will continue on April 14 and is projected to continue through April 26.
- NE corner of 1st Ave N and Republican St. is ongoing and projected to continue through April 15.
- SE corner of 1st Ave N and Republican St. is projected to continue at this location April 26 May 11.
- Sidewalk improvements on the east side of Warren St., between Thomas St. and John St. are projected to be done April 7-20. This sidewalk is currently closed.
- Curb improvements at the intersection of Warren St. and John St. are ongoing and will continue through May 5.
Proper signage, staffing and safety measures will be in place at all locations.
SDOT approved the use of 2nd Ave for inbound and outbound trucks during the hours of
7 am–10 pm Mon.–Fri. and 9 am–10 pm Sat., Sun., and Holidays.
SDOT approved routes for all hours include westbound on Thomas St. to southbound Queen Anne Ave. N.
The Arena MPPCNV is activated.
Construction is allowed 24/7. Impact work hours are limited to daytime work only.
Construction Impact Work Hours:
Monday- Friday 8 am – 5 pm impact workSaturday/Sunday/Holidays
9 am – 5 pm impact work
Interior Work – All work will progress during daytime hours, which includes Saturdays and Sundays from 9 am – 5 pm for impact work. All other work will occur as permitted by the MPPCNV.
- Interior work progresses with elements including fireproofing, lighting installation, framing, drywall work and painting and finishing work.
- Select areas are being moved from temporary to permanent power.
- Arena ribbon boards are being installed and nearing completion.
- Installation of the twin scoreboards is ongoing.
- Catwalk work and installation of lighting in the rigging grid continues.
- Tile and millwork is underway on multiple levels.
- Handrails in the upper deck are being installed and prep work for seating installation continues.
- Build out of ingress/egress at all four corners continues.
- Buildout of the Customer Service office continues.
North Courtyard – Renovation of the North Courtyards (upper and lower) continues. The Courtyards are closed to the public and access will be limited to Seattle Center staff and Resident Organizations. Proper staffing and safety measures are in place. Courtyard work will be done during daytime hours only. As part of the North Courtyard renovation, SDCI has granted approval for the removal of the north segment of the sound wall with the condition that the Arena’s historic curtain wall is sealed.
South Parcel (south of Pottery Northwest) – Connection of Arena sewer lines to City systems is suspended until April 17. Per SDOT, this work will be done during daytime hours on weekends only. All other work will occur as permitted by the MPPCNV.
Construction activity for utility work on Thomas St. between Warren Ave. N and 1st ave. N continues. Pedestrian access is maintained via detours. Proper staffing and safety measures are in place.
Bi-Weekly Arena Meeting – Open to all, the bi-weekly Arena meetings are open house forums to provide project updates and coordinate with stakeholders including but not limited to local businesses, communities, SDOT, SDCI and Seattle Center resident organizations on construction impacts and efforts to support ongoing activities at Seattle Center and in the adjacent communities.
Upcoming schedule:
Date Time Location
April 15th 8 am Zoom Virtual meeting – https://seattlekrakenhockey.zoom.us/j/97458901069
CONSTRUCTION HOTLINE: (206) 401-9896
CONSTRUCTION EMAIL: [email protected]
Follow Climate Pledge Arena on Social Media
Facebook & Instagram: @ClimatePledgeArena
Twitter: @ClimateArena
Website: www.climatepledgearena.com