CONSTRUCTION UPDATE 8.21.2020

Posted on

Early morning delivery of a crane for installation of the parking garage steel truss will take place on Monday, August 24th at approximately 5 am.  

The parking garage steel truss is projected to arrive  on Tuesday, August 25th at approximately 3 am.  This will result in heightened activity but is not expected to generate higher noise levels.

Mural art on the East Sound Wall will have some panels removed for safer and more efficient project access.  They will be saved and placed in storage.  

Removal of the Temporary Roof Support surrounding reconnected footings continues and is projected to be completed by the end of the month.

Steel erection and utilities installation is ongoing and the Arena interior continues to take shape.  

Installation of the landmarked curtain wall is projected to start before the end of August.

The South Buttress has been reconnected and removal of the kickstand is underway.  

Hauling on 1st Ave N will be during the hours of 8 am – 5 pm Monday-Saturday.
SDOT has approved the use of 2nd Ave for inbound and outbound trucks during the hours of
7 am–10 pm Mon.–Fri. and 9 am–10 pm Sat., Sun., and Holidays.

The Arena MPPCNV is activated. 
Construction is allowed 24/7.  Impact work hours are limited to daytime work only.

Construction Impact Work Hours: 
Monday- Friday 8 am – 5 pm impact work
Saturday/Sunday/Holidays
9 am – 5 pm impact work

North Side – Structural steel erection continues along with slab placements that will be starting early morning. Excavation/backfill activities and underground utilities will be installed during evening hours. All work will progress during daytime hours, which includes Saturdays and Sundays from 9 am – 5 pm for impact work.  All other work will occur as permitted by the MPPCNV.

South Side –Foundation placement, shotcrete operations and excavation work continues.  Structural steel erection continues along with slab placements that will be starting early morning. Excavation/backfill activities, along with underground utilities, will be installed during evening hours.  All work will be done during daytime hours, which includes Saturdays and Sundays from 9 am – 5 pm for impact work.  All other work will occur as permitted by the MPPCNV.

Construction activity for utility work on Thomas St. between Warren Ave. N and 1st Ave. N continues.  Pedestrian access will be maintained via detours.  Proper staffing and safety measures will be in place.

West Side – Work includes waterproofing, shotcrete, foundation excavation and new foundation placement. Structural steel erection continues with slab placements that will be starting early morning. Excavation/backfill activities, along with underground utilities, will be installed during evening hours.  All work will be done during daytime hours, which includes Saturdays and Sundays from 9 am – 5 pm for impact work.  All other work will occur as permitted by the MPPCNV.

East Side – Construction work includes waterproofing, shotcrete, foundation excavation and new foundation placement.  Structural steel erection continues along with slab placements that will be starting early morning. Excavation/backfill activities and underground utilities will be installed during evening hours.  All work will be done during daytime hours, which includes Saturdays and Sundays from 9 am – 5 pm for impact work.  All other work will occur as permitted by the MPPCNV.

South Parcel (south of Pottery Northwest) – Horizontal boring of the tunnel, excavation, lagging and tiebacks will continues to progress. 

SDCI has granted a TNV that permits the extension of non-impact construction activity within the South Parcel seven days per week during the windows of 10 pm – 7 am (10 pm – 9 am on weekends and holidays).  The South Parcel TNV has been issued for work through Monday, August 31st.

 Conditions set by SDCI for the South Parcel TNV are as follows:

●      Construction of 12-foot noise barrier around perimeter of South Parcel
●      Limit impact work such as auger shaking, jack hammering, hoe ram use, or vibratory compacting to the hours allowed by SMC 25.08.425.C;
●      Use drilling methods vs impact driving for shoring (i.e., soldier pile walls) and pier installation;
●      Prohibit concrete saws during nighttime hours;
●      lieu of pure-tone, mobile equipment backup alarms, use strobe warning lights or flaggers when possible. When strobe warning lights or flaggers not feasible, construction contractor will use broadband backup alarms. Also, create site logistics that minimize need for mobile equipment to reverse;
●      Prohibit compression brakes;
●      Construct enclosures around stationary equipment;
●      Perform particularly noisy operations during daytime hours or schedule several noisy operations concurrently rather than separately;
●      Employ time constraints for noisy operations to reduce potential impacts during sensitive time periods;
●      Provide training to supervisors to increase awareness of construction noise as it relates to the noise-sensitive surrounding;
●      Use properly sized and maintained mufflers, and if feasible, engine intake silencers and engine enclosures;
●      Turn off idle equipment after no more than five minutes;
●      To reduce noise during loading of soils with cobble, employ one of the following mitigation measures if deemed necessary:
●      Line tuck beds with rubberized noise-absorbing material. Load large cobble using progressive link excavator buckets or similar and ensure loading is performed by a skilled operator or alternatively;
●      Carefully load truck beds first with soils or fine gravels followed by larger pieces of cobble using excavator with progressive link excavator buckets or similar;
●      Installation of a 24-hour construction noise monitoring system to log construction site noise.
●      An additional Noise Monitoring Terminal, NMT4, has been placed on roof of Avalon Cooperative, a 3-story building located at northwest corner of 1st Ave N and John St.

 Bi-Weekly Arena Meeting – Open to all, the bi-weekly Arena meetings are open house forums to provide project updates and coordinate with stakeholders including but not limited to local businesses, communities, SDOT, SDCI and Seattle Center resident organizations on construction impacts and efforts to support ongoing activities at Seattle Center and in the adjacent communities. 

Upcoming schedule: 
Date                   Time      Location
Sept. 3rd             6 pm       Zoom Virtual meeting – https://oakviewgroup.zoom.us/j/96005248370

 

CONSTRUCTION HOTLINE:  (206) 401-9896

CONSTRUCTION EMAIL:  [email protected]

Follow Climate Pledge Arena on Social Media

Facebook & Instagram: @ClimatePledgeArena

Twitter: @ClimateArena 

Website: www.climatepledgearena.com